Main contractor: Energoremont Holding JSC
- Main distribution board LV (MDB) with 2 sections;
- Dry power transformers 1250 кVA, 6/0.4 кV – 2 units;
- Power busbars connectiong the MDB – 2 units;
- Automatic capacitor battery 1000 kVAr (4 х250 kVAr), with communication under protocol IEC61850 - set for substation 1 - 6kV;
- Commisioning and start up with 72 hours tests of the electrical equipment for substation "Chemical base" - 0.4 kV and capacitor batteries set for substation 1 - 6kV.